Cost Benefit Analysis (CBA) for PPPs

ppp foundational concepts Jun 03, 2025
Cost Benefit Analysis PPPs

Cost-Benefit Analysis for Public–Private Partnership Projects

Cost–Benefit Analysis (CBA) is an economic appraisal tool that compares the total social benefits of a project to its total social costs, expressed in common (usually monetary) terms. In the PPP context, CBA measures whether a public infrastructure project (such as a new road, port, or airport) creates enough value for society to justify the resources invested. The “benefits” include all positive effects (e.g. travel time savings, increased trade, job creation, improved connectivity) and the “costs” include all resource uses (construction and operating costs, land acquisition, environmental damage, social dislocations) irrespective of who pays or receives them. In short, a project is economically viable if its discounted benefits to society exceed its discounted costs. CBA explicitly incorporates externalities – for example, it can add the social cost of greenhouse-gas emissions or quantify noise impacts – so that the net social benefit (or welfare) is positive.

Governments and PPP units routinely use CBA to guide infrastructure investment decisions. A standardized CBA provides a common basis for comparing alternatives (for example, “build as PPP” versus “build conventionally” versus “do nothing”) and ensures public funds achieve value for money. Many countries require that all major infrastructure proposals undergo a formal CBA before approval. For PPPs, CBA is often part of the value-for-money (VfM) analysis: it checks that the project yields net benefits to users and taxpayers beyond the simple financial returns to investors. For example, the U.S. “Public Sector Comparator” technique compares the discounted fiscal costs of public vs PPP procurement, but does not capture user‐level benefits (like time saved) without a full CBA. In practice, CBA (sometimes combined with risk adjustment) is the most common method countries use to ensure absolute VfM. An OECD survey found 21 out of 27 governments use CBA (often including life‐cycle costs) to determine value for money in infrastructure. Even when a PPP is financially self‐sustaining, governments perform CBA to demonstrate that the project’s social benefits outweigh its social costs, thereby justifying the use of public contributions or guarantees. PPP units typically provide templates or analytical support so that all relevant effects (economic, environmental, social) are systematically evaluated before a project proceeds.

Steps in an Economic CBA for a PPP Project

An economic CBA follows a structured process, often as follows:

  • Define the project and alternatives: Specify the proposed PPP project (e.g. a new highway or airport) and credible alternatives, including the baseline “do-nothing” or low-cost option. If needed, compare different technical designs or phasing. CBA then measures the incremental impacts of the chosen project versus the next best alternative..

  • List costs and benefits: Identify all relevant impacts on society. Costs typically include capital expenditures, land acquisition, operating costs, and environmental/social mitigation costs. Benefits include user benefits (e.g. travel‐time savings, accident reductions, increased trade flows), wider economic benefits (e.g. agglomeration, productivity gains) and positive externalities (jobs created, improved connectivity). All direct and indirect effects – even those that do not involve market transactions (like health improvements or community displacement) – should be considered to the extent possible.

  • Quantify and monetize impacts: For each cost or benefit, estimate a credible quantity (e.g. vehicle-hours saved, tonnes of emissions) and assign a monetary value. Use market prices where available (e.g. construction bids, fuel costs), or shadow/pricing estimates for non-market impacts. For example, value traveler time by wage rates, and value CO₂ emissions by the social cost of carbon or carbon-market price. Ensure consistency (e.g. use net-of-tax prices and full economic exchange rates for traded goods).

  • Choose analysis period and discount rate: Set the time horizon (usually the infrastructure’s economic life, e.g. 20–30 years or more) and an appropriate social discount rate (often 5–12% depending on country and macro conditions). Future costs and benefits are discounted to present value using:
    NPV=t=0TBtCt(1+r)tNPV = \sum_{t=0}^T \frac{B_t - C_t}{(1+r)^t}
    where BtB_t and CtC_t are benefits and costs in year tt and rr is the discount rate. Using a social (not private) discount rate ensures alignment with public-sector opportunity costs.

  • Compute economic NPV and IRR: Subtract the present value of total costs from benefits to get the Net Present Value (NPV). If NPV is positive, the project increases social welfare. Also calculate the Economic Internal Rate of Return (IRR), which is the discount rate that makes NPV = 0. A project is deemed economically feasible if IRR exceeds the chosen social discount rate (or equivalently, if NPV > 0). (See Box below for definitions.)

  • Sensitivity/uncertainty analysis: Test how results change with key assumptions (e.g. traffic growth, construction costs, carbon price, discount rate). Because project appraisals involve uncertainty, CBA must check whether conclusions are robust. For example, one would check NPV under conservative traffic or benefit estimates, or consider risk buffers for cost overruns. If small changes in inputs make NPV negative, caution is warranted.

Each of these steps should be documented transparently. In practice, analysts build spreadsheets that list streams of costs and benefits year by year, apply discounting, and summarize results in tables or charts. The final CBA report usually highlights the aggregate NPV, benefit–cost ratio, and IRR, along with qualitative comments on non-quantified effects or distributional issues.

Example: Economic CBA for a New International Airport Hub

To illustrate, consider a generic (non-country-specific) CBA for a proposed new international airport hub. The hub is expected to greatly expand air connectivity, promote trade and tourism, but also involves large capital outlay and environmental/social impacts. We make simple illustrative assumptions (in year-0 USD millions unless noted) as follows:

  • Project scope: Build a new international airport terminal and runway. Economic life = 30 years.

  • Costs: Construction cost (CAPEX) = $3,000M at time 0. Annual operations & maintenance = $50M/year. We assume 200 displaced households requiring compensation ($10M total, negligible relative to CAPEX). (All costs are in economic terms, net of taxes/subsidies.)

  • User benefits: Due to the hub, passengers save on travel time and gain new route access. We assume an aggregate “consumer surplus” (travel time savings plus connectivity) of $200M/year. (In reality, benefits would be estimated from traffic forecasts, value-of-time, trade gains, etc.)

  • Other economic benefits: The improved connectivity may boost trade and investment; conservatively, we include an additional $100M/year in wider GDP-related benefits.

  • Environmental costs: Increased flights generate about 1.0 million tonnes of CO₂ per year. At a social carbon price of $50/ton, this is $50M/year in climate damage. Noise impacts and other local pollution could be valued (e.g. as disturbance costs) – for illustration we assume $10M/year in noise/disamenity costs borne by nearby residents.

  • Social benefits: Jobs created and tourism growth are positive but largely captured in the above figures or in GDP gains; relocation costs (see above) are treated as costs.

  • Discount rate: 5% real (social). This reflects a typical public-sector hurdle rate for infrastructure.

Using these assumptions, we tabulate annual net benefits (benefits minus costs) and compute discounted values. A simplified summary is shown below:

Item Value (million $)
Construction (CAPEX) 3,000 (at year 0)
Annual O&M cost 50 per year
Annual travel-time & trade benefit 300 per year (200 + 100)
Annual CO₂ emission cost 50 per year (1Mt at $50/ton)
Annual noise/disamenity cost 10 per year
Economic discount rate 5% (real)
Economic life 30 years
Present value of benefits ≈ 4,224 (30-year annuity at 5%)
Present value of costs ≈ 4,150 (CAPEX + PV of O&M + external costs)
Net Present Value (NPV) ≈ +74
Economic IRR ≈ 5.2%

Calculation details: The present value (PV) of annual net benefits is

t=130(300505010)(1+0.05)t=t=130190(1.05)t4,224.\sum_{t=1}^{30} \frac{(300 - 50 - 50 - 10)}{(1+0.05)^t} = \sum_{t=1}^{30} \frac{190}{(1.05)^t} \approx 4{,}224.

Subtracting the $3,000M initial investment yields NPV ≈ +$74M (see Table). The economic IRR (the rate making NPV zero) is about 5.2%. Because IRR slightly exceeds the 5% discount rate, the project is (just) economically viable under these assumptions.

Figure: A new airport hub can enhance connectivity and economic activity. Its economic appraisal compares all social benefits (e.g. passenger time-savings, trade growth) against all social costs (construction, emissions, noise) over the project’s life.

In this example the NPV is positive but modest. This means projected social benefits barely outweigh costs. We must therefore test key assumptions via sensitivity analysis. For instance:

  • Lower benefits: If actual benefits were only 90% of our base case (e.g. $270M/year instead of $300M), the NPV becomes negative (roughly –$387M) and IRR falls to about 3.8%. In other words, a shortfall in traffic or lower value-of-time would make the project uneconomic (NPV < 0).

  • Higher costs: Similarly, if construction or CO₂ costs were underestimated, NPV would shrink. For example, doubling the effective CO₂ price to $100/ton (so emissions cost $100M/year) would turn net annual benefit negative and wipe out NPV.

  • Discount rate: Using a lower discount rate (say 3%) raises PV of future benefits dramatically (NPV ≈ $920M) because more weight is given to long-term gains. Conversely, a high rate (e.g. 8–10%) would penalize distant benefits and likely yield NPV < 0.

  • Non-quantified factors: Some social impacts (e.g. regional development, or negative effects on displaced communities) may not be fully captured. If these are significant, they should be considered qualitatively alongside the quantitative NPV.

This sensitivity check highlights that the viability of a large PPP project like an airport hub is highly conditional on assumptions. If benefits and costs are estimated accurately, a positive NPV indicates that the project passes the economic test – it “pays back” more to society than it costs. In practice, governments would require such analysis to be reviewed by an independent body (e.g. ministry of finance or a PPP unit) before approving the deal. The analysis should be revisited at bid evaluation to ensure private proposals align with the assumed costs/benefits.

Net Present Value (NPV) and Internal Rate of Return (IRR) are key metrics in CBA. NPV (at a chosen social discount rate) measures the total net social benefit in today’s dollars. A positive NPV means benefits exceed costs. IRR is the break-even discount rate: if IRR > social rate, the project is profitable for society. In our example, IRR ≈ 5.2% barely beats the 5% threshold; any “shock” (e.g. higher costs, lower demand) could lower IRR below the hurdle, flagging caution.

Finally, sensitivity analysis (or Monte Carlo simulations in advanced CBAs) examines how robust these outcomes are. Standard practice (supported by PPP guidelines) is to vary inputs and report the range of NPVs. A project with only a slightly positive NPV under base assumptions is considered high-risk: if small pessimistic changes render NPV negative, governments may decide the PPP is not worth pursuing, or they may seek stronger risk mitigation (like guarantees). In contrast, a large cushion (NPV much bigger than zero even under bad scenarios) would give confidence.

Summary: CBA for PPPs ensures that private-sector financing is applied to projects that serve the public interest. It involves enumerating all economic, environmental, and social costs and benefits of the project, discounting them appropriately, and checking that net benefits are positive. The worked airport example shows how quantitative values (time-savings, CO₂ costs, etc.) can be used to calculate NPV and IRR, and how sensitivity analysis tests the robustness of the findings. By following international best practices (from the World Bank, OECD, ADB, etc.), governments and PPP units can use CBA to screen projects, design value-for-money contracts, and enhance transparency in infrastructure planning.

Key Concepts:

  • Economic Viability: Benefits to society exceed costs. (By contrast, financial viability means user revenues cover costs.)

  • Net Present Value (NPV): Sum of discounted (benefits – costs) over time. NPV > 0 indicates net gain.

  • Internal Rate of Return (IRR): Discount rate at which NPV = 0. The project is acceptable if IRR exceeds the chosen discount rate.

  • Sensitivity Analysis: Evaluating how NPV/IRR change if key assumptions (traffic, costs, discount rate) vary. A robust project has positive NPV across plausible scenarios.

Sources

Guidance for PPP CBA comes from international authorities. For example, global PPP handbooks and certification guides emphasize including all social and environmental effects. World Bank and ADB PPP units recommend CBA as part of project appraisal and value-for-money testing. Empirical reviews (OECD, ITF) show that governments typically mandate CBA or similar methods to justify large infrastructure investments. The example above follows these best-practice principles.

The PPP Alliance is an independent body of knowledge for the advancement of Public-Private Partnership knowledge and best practices.

Interested in joining the community? Become a member today.

Become a Member

Stay connected with news and updates!

Join our mailing list to receive the latest news and updates from our team.
Don't worry, your information will not be shared.

We hate SPAM. We will never sell your information, for any reason.